We are looking at sending the 200 and 400 ton cranes to site instead of the 2 x 100e cranes, as if we hire the 2 x 100e cranes in and there is a delay we will be stuck paying for them once they are mobilised, the 200te and 400te are required at site soon anyway, we need to ensure they can be used as per our offloading method statement and sufficient counterweight is sent up for the repopulation. If we time it correctly could we get the cranes to follow the same escort to site as the blades??
Who is going to be our main point of contact on the ground following the cargo to site, who will liaise with the traffic police and has the experience to do this? Sakda???
I don’t want individual comments to my instructions above back to me, I expect you all to sit down today and discuss via conference or in person and find a way to make this happen. All comments should be directed to Sasa and be well thought through and constructive, not negative and dismissive, we need solutions, not problems, that’s what we are all paid to provide.
Regards