Good Day Miss Bongkoch,
Attached are the order acknowledgements for PO#1089. We booked with APL due to the ocean rate, best price and they have the shortest total transit time. Unfortunately all the vessels are full and the next one we could book has a rail cut of 1/8, ETS west coast Jan. 18, ETA Bangkok Feb. 17th. Evergreen has a ten day longer transit time and is approx. $1000 more. Maersk’s transit is even longer than Evergreen and APL.
We will continue to work with APL to improve the sailing, but unfortunately at this time due to the Christmas and New Year holiday upon us, this is the best we can do at this time.
Thank you for your understanding,
Best regards,