Our original plan is to have the parallel run for 2 weeks with real orders and have the go live decision in this week if we have 3 days consecutively get 100% accuracy on the order receiving and production specification in system. However, so far we only got one day result from MCL and the successful rate is 0%.
Kindly please send out the accuracy report by noon every day and also be reminded that if we couldn’t past the data accuracy KPI for go live by this week, we will consider to postpone the go live date to early 2016 till MCL completed all the necessary configuration in system and get the 3 days 100% pass consecutively.