3.3 Commissioning & Start-up Period Once the unit is pre-commissioned, การแปล - 3.3 Commissioning & Start-up Period Once the unit is pre-commissioned, ไทย วิธีการพูด

3.3 Commissioning & Start-up Period

3.3 Commissioning & Start-up Period
Once the unit is pre-commissioned, the Commissioning Team will conduct the following main activities:
• Purging
• Leak Test / Tightness Test
• Spring Hanger Check
To start with initial Start-up operations assuring that every activity is accomplished smoothly and safely. The Commissioning Subcontractor Team would take care in troubleshooting any operating or process problems, should they arise, and would investigate any operating deviations as they occur. Team will:
a. Develop and Review Specific Operating Instruction
Normally, the procedures and practices outlined in each unit’s operating manual will be followed. However, as these manuals cannot cover every conceivable operating situation, it will be necessary to develop specific operating instructions to cover critical areas of operating as they arise. Any additional operating procedures and practices to operate or control the units will be given either in writing, if time permits, or verbally, if immediate action is required, to operating supervisors. An operating logbook will be kept in order to record the instructions and relevant changes in the operating conditions.
b. Conduct and supervise all activities during the Introduction of Feedstock to the Units
Licensor’s process and operation specialists (if required) will be present for providing advice during the critical first start-up from a technical point of view and will help troubleshoot any problems that arise or investigate any deviations that occur.
The Commissioning team will monitor the plant operations and make any operating changes for stable, efficient operation.
c. Stabilize the Unit
The Commissioning Team will provide to work with process licensors (if required) on how to bring the units on stream and up to design rate. Control variables and flow rates will be specified to stabilize the unit at design rate in preparation for the acceptance test and during the performance test.
d. Conduct Performance Test Run
The Commissioning Team will pompon the procedures guarantee and documentation and witnesses the instrument calibration. During the execution of Performance Test the Initial
Operation Team will conduct the plant according to the procedure already agreed between the AEI and the Client.
0/5000
จาก: -
เป็น: -
ผลลัพธ์ (ไทย) 1: [สำเนา]
คัดลอก!
3.3 &ทดสอบการเดินระบบระยะเวลาเริ่มต้น
เมื่อหน่วยได้รับมอบหมายก่อน ทีมทดสอบการเดินระบบจะดำเนินกิจกรรมหลักดังต่อไปนี้:
• Purging
•ทดสอบรั่ว / ทดสอบชู
•ตรวจสอบแถมสปริง
จะเริ่มต้นด้วย ทำการดำเนินการเริ่มต้นเริ่มมั่นใจที่กิจกรรมทุกอย่างราบรื่น และปลอดภัย ทีมผู้รับเหมาย่อยทดสอบการเดินระบบจะดูแลในการปฏิบัติการแก้ไขปัญหา หรือกระบวนการปัญหา ควรจะเกิดขึ้น และจะตรวจสอบความเบี่ยงเบนใด ๆ ปฏิบัติ ตามที่เกิดขึ้น ทีมจะ:
อ.พัฒนาและตรวจสอบการทำงานคำสั่ง
ปกติ ขั้นตอนการปฏิบัติที่ระบุไว้ในคู่มือการปฏิบัติงานของแต่ละหน่วยจะสามารถปฏิบัติตาม อย่างไรก็ตาม เป็นคู่มือเหล่านี้ไม่สามารถครอบคลุมทุกสถานการณ์ปฏิบัติหลากหลาย มันจะจำเป็นในการพัฒนาคำแนะนำปฏิบัติการครอบคลุมพื้นที่สำคัญของการปฏิบัติจะเกิดขึ้น เพิ่มเติมการทำงานขั้นตอน และวิธีการใช้งาน หรือควบคุมหน่วยจะได้รับอย่างใดอย่างหนึ่งในการเขียน เวลาอนุญาต วาจา หรือถ้าดำเนินการในทันทีจะต้อง ผู้บังคับบัญชาปฏิบัติงาน ล็อกบุ๊คการดำเนินงานจะถูกเก็บไว้เพื่อบันทึกคำแนะนำการเปลี่ยนแปลงที่เกี่ยวข้องในการปฏิบัติงานเงื่อนไข
เกิดปฏิบัติ และกำกับดูแลกิจกรรมทั้งหมดในระหว่างการนำวัตถุดิบให้หน่วย
ผู้อนุญาตของกระบวนการและการดำเนินงานผู้เชี่ยวชาญ (ถ้าจำเป็น) จะอยู่ให้คำแนะนำในช่วงเริ่มแรกสำคัญจากมุมมองของจุดทางเทคนิค และจะช่วยแก้ไขปัญหาใด ๆ ที่เกิดขึ้น หรือตรวจสอบความเบี่ยงเบนใด ๆ ที่เกิดขึ้น.
ทีมทดสอบการเดินระบบจะตรวจสอบการดำเนินงานของโรงงาน และทำการเปลี่ยนแปลงปฏิบัติการมั่นคง มีประสิทธิภาพการดำเนินงาน
c. อยู่ดีหน่วย
ทีมทดสอบการเดินระบบจะให้ทำงานกับกระบวนการผู้ (ถ้าจำเป็น) ในการนำหน่วย ในกระแส และ ได้ออกแบบอัตรา จะระบุตัวแปรควบคุมและอัตราการไหลเพื่อมุ่งหน่วยที่ออกแบบในการเตรียมการ สำหรับการทดสอบการยอมรับ และใน ระหว่าง test. ประสิทธิภาพ
d. ทำประสิทธิภาพการทดสอบรัน
ทีมทดสอบการเดินระบบจะ pompon กระบวนการรับประกันและเอกสาร และสืบพยานการปรับเทียบเครื่องมือ ในระหว่างการดำเนินการผลทดสอบต้น
ทีมดำเนินการจะทำโรงงานตามกระบวนการแล้วตกลงระหว่างคำอ้ายและไคลเอนต์
การแปล กรุณารอสักครู่..
ผลลัพธ์ (ไทย) 2:[สำเนา]
คัดลอก!
3.3 Commissioning & Start-up Period
Once the unit is pre-commissioned, the Commissioning Team will conduct the following main activities:
• Purging
• Leak Test / Tightness Test
• Spring Hanger Check
To start with initial Start-up operations assuring that every activity is accomplished smoothly and safely. The Commissioning Subcontractor Team would take care in troubleshooting any operating or process problems, should they arise, and would investigate any operating deviations as they occur. Team will:
a. Develop and Review Specific Operating Instruction
Normally, the procedures and practices outlined in each unit’s operating manual will be followed. However, as these manuals cannot cover every conceivable operating situation, it will be necessary to develop specific operating instructions to cover critical areas of operating as they arise. Any additional operating procedures and practices to operate or control the units will be given either in writing, if time permits, or verbally, if immediate action is required, to operating supervisors. An operating logbook will be kept in order to record the instructions and relevant changes in the operating conditions.
b. Conduct and supervise all activities during the Introduction of Feedstock to the Units
Licensor’s process and operation specialists (if required) will be present for providing advice during the critical first start-up from a technical point of view and will help troubleshoot any problems that arise or investigate any deviations that occur.
The Commissioning team will monitor the plant operations and make any operating changes for stable, efficient operation.
c. Stabilize the Unit
The Commissioning Team will provide to work with process licensors (if required) on how to bring the units on stream and up to design rate. Control variables and flow rates will be specified to stabilize the unit at design rate in preparation for the acceptance test and during the performance test.
d. Conduct Performance Test Run
The Commissioning Team will pompon the procedures guarantee and documentation and witnesses the instrument calibration. During the execution of Performance Test the Initial
Operation Team will conduct the plant according to the procedure already agreed between the AEI and the Client.
การแปล กรุณารอสักครู่..
ผลลัพธ์ (ไทย) 3:[สำเนา]
คัดลอก!
3.3 การว่าจ้าง&เริ่มขึ้นช่วง
เมื่อหน่วยก่อนมอบหมาย , การว่าจ้างทีมงานจะดำเนินการตามกิจกรรมหลัก :
-
- ทดสอบการรั่วซึม / บริการตรวจสอบทดสอบสปริงแขวน

เริ่มต้นด้วยการเริ่มต้น เริ่มต้นขึ้น มั่นใจว่าทุกกิจกรรมได้อย่างราบรื่นและปลอดภัยการว่าจ้างผู้รับเหมาช่วงทีมที่จะดูแลในปัญหาใด ๆ การดำเนินงานหรือกระบวนการการแก้ไขปัญหาที่พวกเขาควรจะเกิดขึ้น และจะตรวจสอบค่าปฏิบัติการใด ๆที่เกิดขึ้นได้ ทีม :
. พัฒนาและทบทวนเฉพาะปฏิบัติการสอน
โดยปกติ ขั้นตอนและวิธีปฏิบัติที่ระบุไว้ในคู่มือปฏิบัติการของแต่ละหน่วยจะตามมา อย่างไรก็ตามเป็นคู่มือเหล่านี้ไม่สามารถครอบคลุมได้ทุกงาน สถานการณ์ ก็จะต้องพัฒนาเฉพาะคําแนะนําในการปฏิบัติให้ครอบคลุมพื้นที่ที่สำคัญของการดำเนินงานที่พวกเขาเกิดขึ้น เพิ่มเติมขั้นตอนการดำเนินงานและการปฏิบัติงานหรือควบคุมหน่วยจะได้รับทั้งในการเขียน ถ้าเวลาที่อนุญาตให้ หรือด้วยวาจา ถ้าทันทีเป็นสิ่งจำเป็นเพื่อปฏิบัติการ หัวหน้างานการดำเนินงานจะถูกเก็บไว้ในสมุดบันทึก เพื่อบันทึกคําแนะนําและการเปลี่ยนแปลงที่เกี่ยวข้องในเงื่อนไข .
b . การปฏิบัติและการดูแลกิจกรรมทั้งหมดในเบื้องต้นของวัตถุดิบต่อหน่วย
ผู้อนุญาตยินยอมกระบวนการและผู้เชี่ยวชาญการผ่าตัด ( ถ้าจำเป็น ) จะถูกนำเสนอเพื่อให้คำแนะนำในการเริ่มต้นครั้งแรกจากจุดทางเทคนิคของมุมมอง และจะช่วยแก้ไขปัญหาใด ๆที่เกิดขึ้น หรือสืบสวนเบี่ยงเบนที่เกิดขึ้น ทีมงานจะตรวจสอบ
ว่าจ้างโรงงานการทำงานใด ๆ การเปลี่ยนแปลงให้มีเสถียรภาพ ประสิทธิภาพการดำเนินงาน .
C ทำให้หน่วย
การว่าจ้างทีมจะให้ทำงานกับกระบวนการออกใบอนุญาต ( ถ้ามี ) เกี่ยวกับวิธีการนำหน่วยในกระแส และการออกแบบ ในอัตรา ตัวแปรควบคุม และ อัตราการไหลจะถูกกำหนดให้คงที่หน่วยในอัตรา ดีไซน์ ในการเตรียมการสำหรับการทดสอบการยอมรับและในระหว่างการทดสอบประสิทธิภาพการทดสอบประสิทธิภาพ .
D
าวิ่งการว่าจ้างทีมปอม ปอม กระบวนการรับรองและเอกสารและพยานเครื่องมือสอบเทียบ ในระหว่างการดำเนินการของการทดสอบประสิทธิภาพการทำงานที่เริ่มต้นจะนำทีม
พืชตามขั้นตอนที่ได้ตกลงกันระหว่าง AEI
และไคลเอ็นต์
การแปล กรุณารอสักครู่..
 
ภาษาอื่น ๆ
การสนับสนุนเครื่องมือแปลภาษา: กรีก, กันนาดา, กาลิเชียน, คลิงออน, คอร์สิกา, คาซัค, คาตาลัน, คินยารวันดา, คีร์กิซ, คุชราต, จอร์เจีย, จีน, จีนดั้งเดิม, ชวา, ชิเชวา, ซามัว, ซีบัวโน, ซุนดา, ซูลู, ญี่ปุ่น, ดัตช์, ตรวจหาภาษา, ตุรกี, ทมิฬ, ทาจิก, ทาทาร์, นอร์เวย์, บอสเนีย, บัลแกเรีย, บาสก์, ปัญจาป, ฝรั่งเศส, พาชตู, ฟริเชียน, ฟินแลนด์, ฟิลิปปินส์, ภาษาอินโดนีเซี, มองโกเลีย, มัลทีส, มาซีโดเนีย, มาราฐี, มาลากาซี, มาลายาลัม, มาเลย์, ม้ง, ยิดดิช, ยูเครน, รัสเซีย, ละติน, ลักเซมเบิร์ก, ลัตเวีย, ลาว, ลิทัวเนีย, สวาฮิลี, สวีเดน, สิงหล, สินธี, สเปน, สโลวัก, สโลวีเนีย, อังกฤษ, อัมฮาริก, อาร์เซอร์ไบจัน, อาร์เมเนีย, อาหรับ, อิกโบ, อิตาลี, อุยกูร์, อุสเบกิสถาน, อูรดู, ฮังการี, ฮัวซา, ฮาวาย, ฮินดี, ฮีบรู, เกลิกสกอต, เกาหลี, เขมร, เคิร์ด, เช็ก, เซอร์เบียน, เซโซโท, เดนมาร์ก, เตลูกู, เติร์กเมน, เนปาล, เบงกอล, เบลารุส, เปอร์เซีย, เมารี, เมียนมา (พม่า), เยอรมัน, เวลส์, เวียดนาม, เอสเปอแรนโต, เอสโทเนีย, เฮติครีโอล, แอฟริกา, แอลเบเนีย, โคซา, โครเอเชีย, โชนา, โซมาลี, โปรตุเกส, โปแลนด์, โยรูบา, โรมาเนีย, โอเดีย (โอริยา), ไทย, ไอซ์แลนด์, ไอร์แลนด์, การแปลภาษา.

Copyright ©2024 I Love Translation. All reserved.

E-mail: