Dear Kh.Kanyakorn
Now,we stop to get into the old oven from today onwards after importation plan has fewer capabilities than the new plant. The details are as follows:
During 1-22 Feb 15 Master Plan = 969 T
1-13 Feb 15 Actual Intake = 379 T
14-22 Feb 15 Intake Revise Plan = 194. T
So,During 1-22 Feb 15 lost opportunity. = 396 T
And loss of the Man-Hr = 792 Man-Hr
Submited for your kind acknowledgement , Please send Master Plan for next month to use plan for drying