(a) reject the entire respective shipment and require the Seller to repair or replace the rejected items with Goods that comply with the Contact, or,
(b) reject the entire respective shipment, cancel the respective Order(s), and undertake to procure from an alternative source Goods meeting approximately the same specifications required by the Contract, and in such case, the Seller shall pay all costs and other expenses incurred by the Buyer in excess of the purchase price specified in the Contract, or,
(c) undertake to carry out an inspection of the entire respective shipment, and reject the portion of items that do not comply with the Contract requirements. In such case, Seller shall pay all costs incurred by the Buyer for such inspection of the items. Repair or replacement of the rejected Goods shall be directed by the Buyer with the same rights and obligations outlined in sub-clause 12-4) (a) and (b) above