Dear all,
I would like inform you about schedule crushing 16/17.
Detail :
- 14/12/16 : Test new Transformer 20 MW. , CPT check meter "EDMI" and Phase.
- 18/12/16 : Shinko and CPT Check and fix all problem prepare for first Sync.
- 20/12/16 : Start crushing and export line 1
- 21/12/16 : First Sync. EDC line 2
Condition Export :
Crushing Season
TG1 export EDC line2 : 8 MW firmed.
TG2 export EDC line 1 : 3 - 6.5 MW non firmed. ( priority first factory )
TG3 for Factory load.
Remelt Season
TG1 export EDC line1 : 3 - 6.5 MW non firmed , if bagasses enough.
TG2 for Factory load.
TG3 export EDC line 2 : 8 MW firmed.