RCC – M&E comments for condo based

RCC – M&E comments for condo based on drawing submitted on 9-11-2015
GENERAL

1. To submit updated design calculation to justify the design concept

2. To update the design brief, and please state the design is follow what kind of standard, or IEC standard. If it is Thailand practice, please show the relevant guideline

3. Please simplify the electrical circuiting for individual condo unit, no need to follow architect address naming for each unit. For example: Studio unit. DB name shall be CU-ST; the circuit is ST-L1, L2, L3 (for lighting circuit) or P1, P2, P3 (for power, aircond, heater).

4. Please make sure all MEP are coordinated each other. Electrical layout shall show all electrical panel name, and also mechanical panel name. The mechanical panel name, location and its kw shall be exactly same as mechanical layout. The MCCB rating for the mechanical panel shall be same as the feeder from electrical panel. Architect should be notified for all these panel location, and he shall ensure these panel location is appropriate located. All opening on floor or wall shall be make known to both architect and C&S.


Cold water

1. To provide detail water riser shaft with dimension and indicate all pipes and water meters. Please make sure the water meter arrangement is accessible and serviceable.

2. Schematic diagram shall show all pipe type and size, pump flow rate, head, elec kW and etc., tank capacity, same appeared in the layout as well.

3. To indicate tank arrangement with plinth and headroom space to the soffit. To ensure it is accessible and maintainable.

4. Make sure electrical engineer has the same info (label and kW) as per the mechanical drawings.

5. To provide schematic diagram for the cold water pump panel (Transfer pump and roof booster pump)

6. To submit Hydraulic calculation (pump sizing, and tank sizing). Please quote and shown proof on the parameter if it is from any standard or guideline.

7. Is urinal at public toilet is under sensor and used pressured pipes?

8. Provide lockable garden taps as per discussion in the meeting. (20-25m).

9. Indicate bulk water meter location and its size. Make sure architect is being informed the location, as architect may want to add small plant to beautify the location.

10. To provide water pipe tee off for future connection of water sub meter for shops possible of converting to F&B at 1st and 2nd floor. ( Please refer to architect for which shops are relevant.

11. Is there garden at the roof for duplex or penthouse? It shall have garden tap for plant watery purpose.

12. Roof water tank and pump room is located directly above the lift motor room. To make sure it is fully water proof, if not it will damage the lift system or to relocate the tank and pump room to other more suitable location.

13. To provide water hammering arrestor at transfer pipeline.

14. To provide garden tap at sky garden

Sanitary

1. To provide invert level for all inspection pit and external manhole.

2. We notice that you have provided 4 separate pipes for waste pipe, soil pipe, vent pipe, and kitchen discharge pipe. In Malaysia, we only used 2 pipes (combine waste and soil pipe as one vertical stack pipe and vent pipe), and kitchen pipe is discharge direct to floor trap (FT), then from FT to vertical stack pipe.

3. Make sure all necessary ceiling manhole are provided for sanitary inspection joint (especially at 5th floor where the vertical stack joint with the horizontal discharge pipe)

4. What type of material to use at the end of vertical stack joint with horizontal pipe discharge at 5th floor? We worry the end of stack may not be able to withstand the gravity water drop pressure. In Malaysia, we introduce S-Bend for every 8 floor, to reduce this pressure. Alternatively, all joint fittings to main horizontal pipe like elbow, tee, etc shall use cast iron type at this floor.

ACMV

1. We receive your heat load calculation in hard copy. Please email the softcopy.

2. All units shall use split unit, except penthouse, or duplex unit. Particular on type 2A, you have used one big cassette unit for both dining and living room. Please change to 2 nos wall split unit, and make sure no 3 phase split unit is used for small units, except cassette units only.

3. To restudy the CDU unit location and the space allocated for CDU whether sufficient to house all the CDU, and make sure architect is aware and agreed for the location, especially refrigerant pipe for duplex, show how the pipe run to the sky garden, and be aware of the water proofing.

4. Air Cond drainpipe shall not be run horizontally in wall, it shall be dropped vertically direct from indoor unit, and run horizontal in slab to the nearby floor trap or floor drain at balcony.

5. Please show detail hanging (wall bracket and ceiling hung) for the CDU, with recommended spacing from front and back to the wall. (This can be obtained from manufacturer recommendation)

6. Please coordinate the cassette unit with lighting layout, by superimposes both layout in the same drawing, and make sure it does not crashed.

7. To confirm refrigerant pipe thickness is based on R410A refrigerant, not R22.

8. Please make sure refrigerant pipe shall not exceed its maximum distance run as per the manufacturer recommendation.

9. Please make sure exhaust system are provided at all plant room, electrical substation room, lift motor room, and etc. Inform electrical engineer, whether this exhaust fan is interlocking with the light (like toilet), or thermostat control / timer (substation and plant room).

10. Please make sure all these mechanical fan panel locations with label and kW are given to electrical engineer. We have found that your current drawing is not being coordinated with electrical, particular on the location and label.

11. Lift lobby shall have provided ducted ceiling exhaust fan to the wall grille.

12 For corridor at condo, the exhaust fan duct shall be boxed up (250 x 250mm) when run above ceiling at other condo unit. Please coordinate with architect.

13. Please liaise with architect for those exhaust fan duct for F&B shop, which direction to discharge. Please indicate the exhaust pipe direction.

14. Please provide a table to show all exhaust fan size, with the room description served, room volume, and air change designed. Please take note toilet shall use 10 air change, not 2 air change as informed during the meeting.

Fire Protection System

1. Take out sprinkler and smoke detector system for condo unit as agreed by RCC, as it is not a practice in Cambodia and it is also not a international standard requirement.

2. We have found that the wet riser pipe are shown in the sanitary and cold water shaft, which this pipe should be inside the fire hose compartment riser, and please have the detail shown both hosereel and wet riser hose in the fire compartment.

3. To provide automatic CO2 cylinder system for all electrical substation room.

4. To provide fireman intercom system at fire escape staircase, generator room, fire pump room, and the main fire intercom panel shall be located in the main security control room at 1st floor (level 1).

5. No standby fire pump provided? In drawing shown only duty pumpset.

6. 1 set of pump to serve sprinkler, hose reel and wet riser system? If yes, then how to control the flow and pressure of each system? Why there is so many control valve in the pump system, please clarify it usage?

6. Security control room shall be located at the 1st floor, instead of 5th floor, where the fireman shall be able to access direct from main entrance floor to the room at the same floor. Please indicate all the MEP rack inside this control room (Fire Intercom Panel, Main Fire Alarm Panel, CCTV DVR rack and console table (table shall be 600mm away from wall, as many CCTV coaxial cable will be terminated to the DVR), CCTV monitors, Public Address Rack, Audio intercom panel, Access control panel, Lift Supervisory Panel, 24 hrs air cond panel, electrical DB, CATV rack, and etc.

7. Please study where the audio intercom panel, computer racks for structure cabling system,


Electrical & Telephone

1. To submit electrical load calculation based on actual mechanical load rating furnished by mechanical engineer, and also actual lighting and small power point load.

2. To submit voltage drop calculation, cable sizing table for all submain cabling, lux calculation for car park, lobby, plant room, corridor and etc.

3. Please coordinate closely with mechanical engineer for all their mechanical panel location, mechanical loading, mechanical panel label, exhaust fan control (interlocking with lighting, thermostat or timer control)

4. Remember to provide power point for public toilet urinal sensor, access control power point, barrier gate power point, power point for CCTV monitor and all MEP panel in the security control room (1st floor) and control room (5th floor), and please state the power point usage.

5. Circuit for washing machine, kitchen hob, air cond and heater shall be individual circuit by itself, no sharing.

6. All single 13A power outlet shall come with dual international outlet (2 flat hole, and 3 vertical small international hole). The circuit for radial circuit shall not be loop more than 3 power points.

7. All air Cond points and heater points shall come with 20A air Cond switch with pilot light, and cable point with termination connector.

8. To provide DB and weather proof feeder pillar (FP) for compound / landscape lighting, street light, tree light, façade light, roof crown light, and signage light. Please coordinate with architect for such detail and location. All these DB or FP shall be controlled with timer.

9. All DB and meter for retail shops shall be single phase, and condo unit also single phase, except pent house, duplex unit are to use 3 phase. Currently your single lines are all show 3 phase.

10. To provide lux calculation

11.
0/5000
จาก: -
เป็น: -
ผลลัพธ์ (ไทย) 1: [สำเนา]
คัดลอก!
RCC – เห็นคอนโด M & E ตามรูปวาดเขียน 9-11-2015ทั่วไป 1. ต้องคำนวณออกแบบปรับปรุงการออกแบบแนวคิด 2. การปรับปรุงโดยย่อการออกแบบ กรุณาระบุแบบได้ตามชนิดของมาตรฐาน มาตรฐาน IEC ถ้าเป็นไทย กรุณาแสดงผลงานที่เกี่ยวข้อง 3. กรุณาทำ circuiting ไฟฟ้าสำหรับแต่ละคอนโดหน่วย ไม่จำเป็นต้องทำตามสถาปนิกชื่อที่อยู่สำหรับแต่ละหน่วย ตัวอย่าง: หน่วยสตูดิโอ ชื่อ DB จะ CU-เซนต์ วงจรเป็นเซนต์ L1, L2, L3 (สำหรับวงจรไฟ) หรือ P1, p 2, P3 (สำหรับพลังงาน ทัด ฮีตเตอร์) 4. กรุณาตรวจสอบว่า MEP ทั้งหมดจะร่วมกัน ไฟฟ้าเค้าจะแสดงทั้งหมดชื่อแผงไฟฟ้า และชื่อแผงควบคุมเครื่องจักรกล ชื่อแผงเครื่องกล ตำแหน่ง และกิโลวัตต์ของจะว่าเหมือนเค้าโครงเครื่องจักรกล จัดอันดับ MCCB แผงเครื่องจะเหมือนกับที่ป้อนจากแผงไฟฟ้า สถาปนิกควรทราบทั้งหมดเหล่านี้แผงที่ตั้ง และเขาจะให้เหล่านี้แผงที่ตั้งที่เหมาะสมอยู่ เปิดทั้งหมดบนพื้นหรือผนังจะต้องให้ทราบทั้งสถาปนิก C และ s ได้ น้ำเย็น 1. เพื่อให้รายละเอียดน้ำ riser เพลาขนาด และระบุท่อทั้งหมด และน้ำเมตร กรุณาตรวจสอบว่า จัดเมตรน้ำจะสามารถเข้าถึงได้ และกล้า 2. แผนผังวงจรไดอะแกรมจะแสดงทั้งหมดท่อชนิดและขนาด อัตราการไหลปั๊ม หัว elec กิโลวัตต์และฯลฯ ความจุถัง เดียวกันปรากฏในเค้าโครงเช่นการ 3. เพื่อบ่งชี้จัดถัง มีพื้นที่ฐานประทักษิณและ headroom soffit เพื่อให้สามารถเข้าถึงได้ และ maintainable 4. ให้แน่ใจว่าวิศวกรไฟฟ้าเดียวกันข้อมูล (ป้ายชื่อและ kW) ตามภาพวาดเครื่องกลได้ 5. เพื่อให้ไดอะแกรมแผนผังวงจรแผงเครื่องสูบน้ำเย็น (โอนปั๊มและปั๊มหลังคา) 6. การส่งคำนวณไฮดรอลิก (ขนาดปั๊ม และขนาดถัง) โปรดเสนอราคาและแสดงหลักฐานบนพารามิเตอร์ถ้ามันมาจากมาตรฐานหรือหลักเกณฑ์ใด ๆ 7. คือ ปัสสาวะที่ห้องน้ำสาธารณะภายใต้เซนเซอร์ และใช้ท่อให้ 8. ให้ก๊อกคือสวนตามในการประชุม (20-25 เมตร) 9. ระบุที่เก็บสินค้าจำนวนมากน้ำเมตรและขนาด แน่ใจว่าสถาปนิกมีการทราบถึงตำแหน่งที่ตั้ง เป็นสถาปนิกอาจต้องเพิ่มขนาดเล็กโรงงานประดิษฐ์ประดอยที่ตั้ง 10. เพื่อให้ท่อน้ำทีปิดการเชื่อมต่อในอนาคตของน้ำย่อยเมตรสำหรับร้านค้าสามารถแปลง F & B ชั้น 1 และ 2 (โปรดดูสถาปนิกสำหรับร้านค้าใดเกี่ยวข้อง 11. มีสวนที่หลังคาสำหรับเพล็กซ์เพนเฮ้าส์หรือไม่ มันจะมีประปาสวนพืชน้ำประสงค์ 12. หลังคาน้ำถังและปั๊มห้องตั้งอยู่เหนือห้องเครื่องลิฟท์โดยตรง ให้แน่ใจว่า มีครบกันน้ำ ถ้า ไม่มันจะเสียระบบลิฟท์ หรือย้ายถังและห้องปั๊มไปสถานอื่น ๆ ที่เหมาะขึ้น 13. การให้น้ำ arrestor ตบที่ขั้นตอนการโอนย้าย 14. ให้แตะสวนที่สวนฟ้า Sanitary 1. To provide invert level for all inspection pit and external manhole. 2. We notice that you have provided 4 separate pipes for waste pipe, soil pipe, vent pipe, and kitchen discharge pipe. In Malaysia, we only used 2 pipes (combine waste and soil pipe as one vertical stack pipe and vent pipe), and kitchen pipe is discharge direct to floor trap (FT), then from FT to vertical stack pipe. 3. Make sure all necessary ceiling manhole are provided for sanitary inspection joint (especially at 5th floor where the vertical stack joint with the horizontal discharge pipe) 4. What type of material to use at the end of vertical stack joint with horizontal pipe discharge at 5th floor? We worry the end of stack may not be able to withstand the gravity water drop pressure. In Malaysia, we introduce S-Bend for every 8 floor, to reduce this pressure. Alternatively, all joint fittings to main horizontal pipe like elbow, tee, etc shall use cast iron type at this floor. ACMV 1. We receive your heat load calculation in hard copy. Please email the softcopy. 2. All units shall use split unit, except penthouse, or duplex unit. Particular on type 2A, you have used one big cassette unit for both dining and living room. Please change to 2 nos wall split unit, and make sure no 3 phase split unit is used for small units, except cassette units only. 3. To restudy the CDU unit location and the space allocated for CDU whether sufficient to house all the CDU, and make sure architect is aware and agreed for the location, especially refrigerant pipe for duplex, show how the pipe run to the sky garden, and be aware of the water proofing. 4. Air Cond drainpipe shall not be run horizontally in wall, it shall be dropped vertically direct from indoor unit, and run horizontal in slab to the nearby floor trap or floor drain at balcony. 5. Please show detail hanging (wall bracket and ceiling hung) for the CDU, with recommended spacing from front and back to the wall. (This can be obtained from manufacturer recommendation) 6. Please coordinate the cassette unit with lighting layout, by superimposes both layout in the same drawing, and make sure it does not crashed. 7. To confirm refrigerant pipe thickness is based on R410A refrigerant, not R22. 8. Please make sure refrigerant pipe shall not exceed its maximum distance run as per the manufacturer recommendation. 9. Please make sure exhaust system are provided at all plant room, electrical substation room, lift motor room, and etc. Inform electrical engineer, whether this exhaust fan is interlocking with the light (like toilet), or thermostat control / timer (substation and plant room). 10. Please make sure all these mechanical fan panel locations with label and kW are given to electrical engineer. We have found that your current drawing is not being coordinated with electrical, particular on the location and label. 11. Lift lobby shall have provided ducted ceiling exhaust fan to the wall grille. 12 For corridor at condo, the exhaust fan duct shall be boxed up (250 x 250mm) when run above ceiling at other condo unit. Please coordinate with architect. 13. Please liaise with architect for those exhaust fan duct for F&B shop, which direction to discharge. Please indicate the exhaust pipe direction. 14. Please provide a table to show all exhaust fan size, with the room description served, room volume, and air change designed. Please take note toilet shall use 10 air change, not 2 air change as informed during the meeting. Fire Protection System 1. Take out sprinkler and smoke detector system for condo unit as agreed by RCC, as it is not a practice in Cambodia and it is also not a international standard requirement. 2. We have found that the wet riser pipe are shown in the sanitary and cold water shaft, which this pipe should be inside the fire hose compartment riser, and please have the detail shown both hosereel and wet riser hose in the fire compartment. 3. To provide automatic CO2 cylinder system for all electrical substation room. 4. To provide fireman intercom system at fire escape staircase, generator room, fire pump room, and the main fire intercom panel shall be located in the main security control room at 1st floor (level 1). 5. No standby fire pump provided? In drawing shown only duty pumpset. 6. 1 set of pump to serve sprinkler, hose reel and wet riser system? If yes, then how to control the flow and pressure of each system? Why there is so many control valve in the pump system, please clarify it usage? 6. Security control room shall be located at the 1st floor, instead of 5th floor, where the fireman shall be able to access direct from main entrance floor to the room at the same floor. Please indicate all the MEP rack inside this control room (Fire Intercom Panel, Main Fire Alarm Panel, CCTV DVR rack and console table (table shall be 600mm away from wall, as many CCTV coaxial cable will be terminated to the DVR), CCTV monitors, Public Address Rack, Audio intercom panel, Access control panel, Lift Supervisory Panel, 24 hrs air cond panel, electrical DB, CATV rack, and etc. 7. Please study where the audio intercom panel, computer racks for structure cabling system, Electrical & Telephone 1. To submit electrical load calculation based on actual mechanical load rating furnished by mechanical engineer, and also actual lighting and small power point load. 2. To submit voltage drop calculation, cable sizing table for all submain cabling, lux calculation for car park, lobby, plant room, corridor and etc. 3. Please coordinate closely with mechanical engineer for all their mechanical panel location, mechanical loading, mechanical panel label, exhaust fan control (interlocking with lighting, thermostat or timer control)
4. Remember to provide power point for public toilet urinal sensor, access control power point, barrier gate power point, power point for CCTV monitor and all MEP panel in the security control room (1st floor) and control room (5th floor), and please state the power point usage.

5. Circuit for washing machine, kitchen hob, air cond and heater shall be individual circuit by itself, no sharing.

6. All single 13A power outlet shall come with dual international outlet (2 flat hole, and 3 vertical small international hole). The circuit for radial circuit shall not be loop more than 3 power points.

7. All air Cond points and heater points shall come with 20A air Cond switch with pilot light, and cable point with termination connector.

8. To provide DB and weather proof feeder pillar (FP) for compound / landscape lighting, street light, tree light, façade light, roof crown light, and signage light. Please coordinate with architect for such detail and location. All these DB or FP shall be controlled with timer.

9. All DB and meter for retail shops shall be single phase, and condo unit also single phase, except pent house, duplex unit are to use 3 phase. Currently your single lines are all show 3 phase.

10. To provide lux calculation

11.
การแปล กรุณารอสักครู่..
ผลลัพธ์ (ไทย) 2:[สำเนา]
คัดลอก!
RCC - M & E ความคิดเห็นสำหรับคอนโดอยู่บนพื้นฐานของการวาดภาพส่งมาใน 2015/09/11
ทั่วไป1 ที่จะส่งการคำนวณการออกแบบปรับปรุงที่จะปรับแนวคิดการออกแบบ2 ในการอัพเดตสั้น ๆ ออกแบบและโปรดระบุการออกแบบคือการปฏิบัติตามสิ่งที่ชนิดของมาตรฐานหรือมาตรฐาน IEC ถ้ามันคือการปฏิบัติที่ประเทศไทยโปรดแสดงแนวทางที่เกี่ยวข้อง3 กรุณาลดความซับซ้อนของลัดวงจรไฟฟ้าสำหรับคอนโดแต่ละคนไม่จำเป็นต้องทำตามที่อยู่สำหรับการตั้งชื่อสถาปนิกแต่ละหน่วย ตัวอย่างเช่นหน่วยสตูดิโอ ชื่อฐานข้อมูลจะเป็น CU-ST; วงจร ST-L1, L2, L3 (วงจรแสง) หรือ P1, P2, P3 (อำนาจ Aircond, เครื่องทำน้ำอุ่น). 4 โปรดตรวจสอบว่า MEP ทั้งหมดมีการประสานงานซึ่งกันและกัน รูปแบบไฟฟ้าจะแสดงชื่อแผงไฟฟ้าและยังเป็นชื่อแผงกล ชื่อแผงกลสถานที่และกิโลวัตต์ของตนจะไม่เหมือนเดิมตรงตามรูปแบบกล คะแนน MCCB สำหรับแผงกลจะเป็นเช่นเดียวกับที่ป้อนจากแผงไฟฟ้า สถาปนิกควรได้รับแจ้งทั้งหมดที่ตั้งแผงเหล่านี้และให้แน่ใจว่าเขาจะตั้งแผงเหล่านี้มีความเหมาะสมอยู่ เปิดบนพื้นหรือผนังทั้งหมดจะถูกทำให้เป็นที่รู้จักกันทั้งสถาปนิกและ C & S. น้ำเย็น1 เพื่อให้เพลาน้ำไรเซอร์ที่มีรายละเอียดมิติและระบุท่อและมาตรวัดน้ำ โปรดตรวจสอบว่าการจัดมิเตอร์น้ำสามารถเข้าถึงและซ่อมแซม. 2 แผนภาพจะแสดงชนิดท่อทุกขนาดและอัตราการไหลของปั๊มหัวกิโลวัตต์ไฟฟ้าและอื่น ๆ , ความจุของถังเดียวกันปรากฏในรูปแบบเช่นกัน. 3 เพื่อบ่งชี้ถึงการจัดถังที่มีฐานและพื้นที่รองรับการ soffit เพื่อให้แน่ใจว่าจะสามารถเข้าถึงและบำรุงรักษา. 4 ทำให้วิศวกรไฟฟ้าแน่ใจว่ามีข้อมูลเดียวกัน (ฉลากและกิโลวัตต์) ตามภาพวาดกล. 5 เพื่อให้แผนภาพสำหรับปั๊มน้ำเย็นแผง (ปั๊มโอนและปั๊มหลังคา) 6 ที่จะส่งคำนวณไฮโดรลิค (ขนาดปั๊มและขนาดถัง) กรุณาอ้างอิงและหลักฐานที่แสดงบนพารามิเตอร์ถ้ามันเป็นจากมาตรฐานหรือแนวทาง. 7 เป็นปัสสาวะที่ห้องน้ำสาธารณะอยู่ภายใต้การเซ็นเซอร์และใช้ท่อกดดัน? 8 ให้ก๊อกสวนล็อคตามการอภิปรายในที่ประชุม (20-25m). 9 ระบุที่ตั้งมิเตอร์น้ำจำนวนมากและขนาดของมัน ทำให้สถาปนิกแน่ใจว่าได้รับแจ้งจากสถานที่ตั้งเป็นสถาปนิกอาจต้องการเพิ่มโรงงานขนาดเล็กในการตกแต่งสถานที่. 10 เพื่อให้ทีท่อน้ำออกสำหรับการเชื่อมต่ออนาคตของน้ำย่อยเมตรสำหรับร้านค้าเป็นไปได้ของการแปลง F & B ที่ 1 และชั้นที่ 2 (โปรดดูสถาปนิกที่ร้านค้าที่เกี่ยวข้อง. 11. มีสวนหลังคาสำหรับเพล็กซ์เพนเฮ้าส์หรือมันจะต้องมีการแตะเพื่อวัตถุประสงค์ในสวนน้ำพืช. 12. ถังเก็บน้ำบนหลังคาและห้องปั๊มตั้งอยู่เหนือห้องมอเตอร์ลิฟท์ . เพื่อให้แน่ใจว่ามันเป็นอย่างกันน้ำหากไม่ได้จะเกิดความเสียหายระบบลิฟท์หรือจะย้ายรถถังและปั๊มห้องพักอื่น ๆ สถานที่ที่เหมาะสมมากขึ้น. 13 เพื่อให้ arrestor ตอกน้ำท่อโอน. 14 เพื่อให้การประปาสวน ท้องฟ้าสวนสุขาภิบาล1. เพื่อให้ระดับกลับสำหรับทุกหลุมท่อระบายน้ำและการตรวจสอบภายนอก. 2. เราสังเกตเห็นว่าคุณได้ให้ 4 ท่อที่แยกต่างหากสำหรับท่อเสียดินท่อระบายท่อและท่อระบายครัว. ในประเทศมาเลเซียเราใช้เพียง 2 ท่อ (รวมของเสียและท่อดินเป็นหนึ่งในท่อสแต็คในแนวตั้งและท่อระบาย) และท่อครัวจำหน่ายโดยตรงกับดักชั้น (FT) แล้วจาก FT ท่อแนวตั้งสแต็ค. 3 ให้แน่ใจว่าทุกเพดานท่อระบายน้ำที่จำเป็นจะมีให้สำหรับสุขาภิบาล ร่วมกันตรวจสอบ (โดยเฉพาะที่ชั้น 5 ที่ร่วมสแต็คในแนวตั้งกับท่อระบายแนวนอน) 4 สิ่งที่ชนิดของวัสดุที่จะใช้ในตอนท้ายของการร่วมทุนกับสแต็คในแนวตั้งแนวนอนปล่อยท่อที่ชั้น 5? เรากังวลในตอนท้ายของสแต็คอาจจะไม่สามารถที่จะทนต่อแรงโน้มถ่วงน้ำความดันลดลง ในประเทศมาเลเซียเราแนะนำ S-เบนด์สำหรับทุก 8 ชั้นเพื่อลดความดันนี้ อีกวิธีหนึ่งคืออุปกรณ์ทั้งหมดร่วมกับท่อแนวนอนหลักเช่นข้อศอก, ที ฯลฯ จะใช้ประเภทเหล็กที่ชั้นนี้. ACMV 1 เราได้รับการคำนวณภาระความร้อนของคุณในการคัดลอกยาก กรุณาส่งอีเมล์ softcopy ได้. 2 ทุกหน่วยงานจะต้องใช้หน่วยแยกยกเว้นเพิงหรือหน่วยเพล็กซ์ โดยเฉพาะอย่างยิ่งใน 2A ชนิดที่คุณได้ใช้หน่วยหนึ่งเทปที่ยิ่งใหญ่สำหรับทั้งการรับประทานอาหารและห้องนั่งเล่น กรุณาเปลี่ยน 2 กัดกร่อนผนังหน่วยแยกและให้แน่ใจว่าไม่มีหน่วยแยกระยะที่ 3 จะใช้สำหรับหน่วยเล็กยกเว้นหน่วยเทปเท่านั้น. 3 เพื่อ restudy ตำแหน่งหน่วย CDU และพื้นที่ที่จัดสรรไว้สำหรับ CDU ว่าเพียงพอที่จะบ้าน CDU ทั้งหมดและทำให้สถาปนิกแน่ใจว่าจะทราบและเห็นด้วยสำหรับสถานที่ท่อสารทำความเย็นโดยเฉพาะอย่างยิ่งสำหรับเพล็กซ์, แสดงให้เห็นว่าการทำงานของท่อสวนลอยฟ้าและจะ ตระหนักถึงการตรวจสอบน้ำ. 4 ท่อระบายน้ำแอร์จะไม่ถูกเรียกใช้ในแนวนอนในผนังก็จะได้รับการปรับตัวลดลงในแนวตั้งตรงจากหน่วยในร่มและทำงานในแนวนอนแผ่นกับดักชั้นใกล้เคียงหรือท่อระบายน้ำชั้นที่ระเบียง. 5 กรุณาแสดงรายละเอียดที่แขวน (ยึดผนังและเพดานแขวน) สำหรับ CDU มีระยะห่างที่แนะนำจากด้านหน้าและด้านหลังกับผนัง (ซึ่งสามารถหาได้จากคำแนะนำของผู้ผลิต) 6 โปรดประสานงานหน่วยเทปคาสเซ็ทที่มีรูปแบบแสงโดย superimposes ทั้งสองรูปแบบในการวาดภาพเหมือนกันและทำให้แน่ใจว่าจะไม่ตก. 7 เพื่อยืนยันความหนาของท่อสารทำความเย็นจะขึ้นอยู่กับสารทำความเย็น R410A ไม่ R22. 8 กรุณาตรวจสอบให้แน่ใจว่าท่อสารทำความเย็นจะต้องไม่เกินระยะทางสูงสุดที่ทำงานตามคำแนะนำของผู้ผลิต. 9 กรุณาตรวจสอบให้แน่ใจว่าระบบไอเสียให้ที่ห้องพักทุกโรงพักสถานีไฟฟ้า, ลิฟท์ห้องพักยนต์และอื่น ๆ แจ้งวิศวกรไฟฟ้าไม่ว่าจะเป็นพัดลมดูดอากาศนี้จะถูกเชื่อมต่อกันด้วยแสง (เช่นห้องน้ำ) หรือควบคุมอุณหภูมิ / จับเวลา (สถานีย่อยและโรงงาน ห้อง). 10 โปรดตรวจสอบว่าสถานที่เหล่านี้แผงแฟนกลที่มีป้ายและกิโลวัตต์ให้กับวิศวกรไฟฟ้า เราพบว่าการวาดภาพปัจจุบันของคุณจะไม่ได้รับการประสานงานกับไฟฟ้าโดยเฉพาะอย่างยิ่งกับสถานที่และป้าย. 11 ล็อบบี้ลิฟท์จะมีเพดานให้ ducted พัดลมดูดอากาศเพื่อกระจังผนัง. 12 ทางเดินที่คอนโด, ท่อพัดลมดูดอากาศจะได้รับการบรรจุอยู่ในกล่องขึ้นไป (250 x 250 มม) เมื่อทำงานเหนือฝ้าเพดานที่คอนโดอื่น ๆ โปรดประสานงานกับสถาปนิก. 13 กรุณาติดต่อประสานงานกับสถาปนิกท่อพัดลมดูดอากาศเหล่านั้นสำหรับร้าน F & B ซึ่งทิศทางที่จะปล่อย กรุณาระบุทิศทางท่อไอเสีย. 14 โปรดระบุตารางเพื่อแสดงขนาดพัดลมดูดอากาศทั้งหมดที่มีรายละเอียดของห้องเสิร์ฟปริมาณห้องพักและการเปลี่ยนแปลงของอากาศได้รับการออกแบบ กรุณาใช้ห้องน้ำทราบการเปลี่ยนแปลงจะต้องใช้อากาศ 10 ไม่ 2 การเปลี่ยนแปลงของอากาศตามที่แจ้งในระหว่างการประชุม. ไฟระบบป้องกัน1 ที่จะออกจากหัวฉีดและระบบการตรวจจับควันสำหรับคอนโดตามที่ตกลงกันโดย RCC ขณะที่มันไม่ได้มีการปฏิบัติในประเทศกัมพูชาและก็ยังไม่ได้เป็นความต้องการตามมาตรฐานสากล. 2 เราพบว่าท่อไรเซอร์ที่เปียกจะแสดงในเพลาน้ำสุขาภิบาลและเย็นซึ่งท่อนี้ควรจะยกระดับช่องภายในท่อดับเพลิงและโปรดให้รายละเอียดที่แสดงทั้ง hosereel และท่อไรเซอร์เปียกในช่องไฟ. 3 เพื่อให้ระบบถัง CO2 อัตโนมัติสำหรับห้องพักทุกสถานีไฟฟ้า. 4 เพื่อให้ระบบอินเตอร์คอมที่พนักงานดับเพลิงดับเพลิงบันไดหนีห้องกำเนิดห้องสูบน้ำดับเพลิงและแผงอินเตอร์คอมไฟหลักจะต้องอยู่ในห้องควบคุมการรักษาความปลอดภัยหลักที่ชั้น 1 (ระดับ 1). 5 ไม่มีสูบน้ำดับเพลิงสแตนด์บายให้? ในการวาดภาพที่แสดง Pumpset หน้าที่เพียง. 6 1 ชุดของเครื่องสูบน้ำที่จะให้บริการฉีดรีลท่อไรเซอร์และระบบการเปียก? ถ้าใช่แล้ววิธีการควบคุมการไหลและความดันของแต่ละระบบ? ทำไมมีวาล์วควบคุมจำนวนมากในระบบเครื่องสูบน้ำโปรดชี้แจงการใช้งาน? 6 ห้องควบคุมการรักษาความปลอดภัยจะต้องตั้งอยู่ที่ชั้น 1 แทนชั้น 5 ที่พนักงานดับเพลิงจะสามารถเข้าถึงได้โดยตรงจากพื้นทางเข้าหลักไปที่ห้องที่ชั้นเดียวกัน กรุณาระบุทุกชั้น MEP ภายในห้องควบคุมนี้ (ไฟอินเตอร์แผงสัญญาณเตือนไฟไหม้หลักแผง, ชั้นวางกล้องวงจรปิดบันทึกภาพและโต๊ะคอนโซล (ตารางจะต้อง 600mm ห่างจากผนัง, กล้องวงจรปิดมากที่สุดเท่าที่คู่สายจะถูกยกเลิกการบันทึกภาพ) ตรวจสอบกล้องวงจรปิด แร็คอยู่สาธารณะแผงอินเตอร์คอมเสียง, แผงควบคุมการเข้าถึงยกแผงกำกับตลอด 24 ชั่วโมงแผงอากาศ cond, DB ไฟฟ้าชั้น CATV และอื่น ๆ7. โปรดศึกษาที่แผงอินเตอร์คอมเสียง, ชั้นวางคอมพิวเตอร์สำหรับโครงสร้างระบบสายไฟฟ้าและโทรศัพท์1. ในการส่งการคำนวณภาระไฟฟ้าขึ้นอยู่กับคะแนนโหลดทางกลที่เกิดขึ้นจริงตกแต่งโดยวิศวกรเครื่องกลและแสงที่เกิดขึ้นจริงและโหลดจุดไฟขนาดเล็ก. 2. ส่งคำนวณแรงดันไฟฟ้าลดลงตารางขนาดสายสาย submain ทั้งหมดคำนวณลักซ์สำหรับรถ สวนสาธารณะล็อบบี้ห้องพืชทางเดินและอื่น ๆ3. โปรดประสานงานอย่างใกล้ชิดกับวิศวกรเครื่องกลสำหรับทุกสถานที่แผงกลของพวกเขาในการโหลดกลฉลากแผงกลการควบคุมพัดลมดูดอากาศ (ที่เชื่อมต่อกันเทอร์โมที่มีแสงหรือการควบคุมการจับเวลา) 4 โปรดจำไว้ว่าจะให้จุดไฟสำหรับห้องน้ำสาธารณะเซ็นเซอร์ปัสสาวะจุดไฟการควบคุมการเข้าถึงจุดไฟประตูกั้นจุดไฟสำหรับกล้องวงจรปิดตรวจสอบและทุกแผง MEP ในห้องควบคุมการรักษาความปลอดภัย (ชั้น 1) และห้องควบคุม (ชั้น 5) และโปรดรัฐ การใช้งานที่จุดไฟ. 5 วงจรสำหรับเครื่องซักผ้า, เครื่องซักผ้าห้องครัวแอร์เครื่องทำน้ำอุ่นและจะเป็นวงจรของแต่ละบุคคลด้วยตัวเองร่วมกัน no. 6 ทั้งหมดปลั๊กไฟ 13A เดียวจะมาพร้อมกับเต้าเสียบระหว่างประเทศคู่ (2 หลุมแบนและแนวตั้ง 3 หลุมระหว่างประเทศขนาดเล็ก) วงจรวงจรรัศมีไม่ต้องห่วงมากกว่า 3 จุดพลังงาน. 7 ทุกจุด Cond อากาศและจุดเครื่องทำน้ำอุ่นจะมาพร้อมกับสวิทช์ 20A อากาศ Cond ด้วยแสงนักบินและจุดเชื่อมต่อเคเบิลที่มีการเลิกจ้าง. 8 เพื่อให้ฐานข้อมูลและเสาป้อนหลักฐานสภาพอากาศ (FP) สำหรับสาร / แสงภูมิไฟถนน, ไฟต้นไม้, ไฟด้านหน้าแสงมงกุฎหลังคาและไฟป้าย โปรดประสานงานกับสถาปนิกเพื่อดูรายละเอียดเช่นสถานที่ตั้ง ทั้งหมดเหล่านี้ DB หรือ FP จะถูกควบคุมด้วยการจับเวลา. 9 ทั้งหมด DB เมตรและร้านค้าปลีกจะต้องมีขั้นตอนเดียวและคอนโดยังเฟสเดียวยกเว้นบ้านถูกกักหน่วยเพล็กซ์ที่ใช้งาน 3 เฟส ปัจจุบันสายเดียวของคุณจะแสดงทั้งหมด 3 เฟส. 10 เพื่อให้การคำนวณลักซ์11

























































































































การแปล กรุณารอสักครู่..
ผลลัพธ์ (ไทย) 3:[สำเนา]
คัดลอก!
RCC ) M & E ความคิดเห็นสำหรับคอนโด โดยใช้ภาพวาด เป็น 9-11-2015
ทั่วไป

1 ที่จะส่งการปรับปรุงการออกแบบการปรับแนวคิดการออกแบบ

2 การปรับปรุงการออกแบบโดยย่อ และกรุณาระบุแบบตามชนิดของมาตรฐาน หรือ IEC มาตรฐาน ถ้าจะฝึกในประเทศไทย โปรดแสดงแนวทางที่เกี่ยวข้อง

3 ช่วยลดความซับซ้อนของ circuiting ไฟฟ้าหน่วยคอนโดแต่ละไม่ต้องตั้งชื่อตามสถาปนิกที่อยู่ในแต่ละหน่วย ตัวอย่างเช่น : หน่วยสตูดิโอ ชื่อฐานข้อมูลจะต้อง cu-st ; วงจรเป็น st-l1 , L2 , L3 ( วงจรแสงสว่างหรือ P1 , P2 , P3 ( อำนาจ aircond ฮีตเตอร์ )

4 . กรุณาตรวจสอบให้แน่ใจว่าทั้งหมดจะถูกประสานงานแต่ละอื่น ๆ ผังไฟฟ้าจะแสดงทั้งหมดที่แผงไฟชื่อ และชื่อแผงยังกล ชื่อแผงเครื่องจักรกลที่ตั้งและขนาดของมันจะเหมือนกันแบบกล การจัดอันดับ MCCB สำหรับแผงจักรกลจะเหมือนกับแผงป้อนจากไฟฟ้า สถาปนิกควรแจ้งตำแหน่งแผงเหล่านี้ และเขาจะให้แน่ใจว่าเหล่านี้แผงที่ตั้งที่เหมาะสมอยู่ เปิดบนพื้นหรือผนัง จะทำให้รู้จักทั้งสถาปนิกและ C & S .

น้ำเย็น

1เพื่อให้เพลา Riser น้ำรายละเอียดกับมิติและระบุท่อทั้งหมดและเมตรน้ำ กรุณาตรวจสอบให้แน่ใจว่าจัดมิเตอร์น้ำ สามารถเข้าถึงได้และเป็นประโยชน์

2 แผนภาพจะแสดงทุกประเภทและขนาดท่อ , หัวปั๊ม , อัตราการไหล กิโลวัตต์ ผลไม้ ฯลฯ ความจุถังเดียวกัน ปรากฏในรูปแบบเช่นกัน

3 ถึงข้อตกลงกับแท่นด้วยรถถังและพื้นที่ soffit .เพื่อให้แน่ใจว่ามันสามารถเข้าถึงได้และ maintainable .

4 . ให้แน่ใจว่ามีข้อมูลเดียวกันวิศวกรไฟฟ้า ( ป้ายชื่อและกิโลวัตต์ ) ต่อเขียนแบบเครื่องกล

5 ให้แผนภาพสำหรับน้ำเย็นปั๊ม ( ปั๊ม และปั๊มแผงหลังคา )

6 ส่งการคำนวณไฮดรอลิก ( ปั๊มขนาด และถังขนาด )กรุณาพูดและแสดงหลักฐานในพารามิเตอร์ถ้ามันจากการใด ๆ มาตรฐานหรือแนวปฏิบัติ

7 เป็นโถปัสสาวะที่ห้องน้ำสาธารณะภายใต้เซ็นเซอร์และใช้กดดันท่อ ?

8 มีก๊อกสวนล็อคต่อการอภิปรายในการประชุม ( 20-25m ) .

9 ระบุเป็นกลุ่มน้ำเครื่องวัดที่ตั้งและขนาดของมัน ให้สถาปนิกได้ถูกแจ้งสถานที่
การแปล กรุณารอสักครู่..
 
ภาษาอื่น ๆ
การสนับสนุนเครื่องมือแปลภาษา: กรีก, กันนาดา, กาลิเชียน, คลิงออน, คอร์สิกา, คาซัค, คาตาลัน, คินยารวันดา, คีร์กิซ, คุชราต, จอร์เจีย, จีน, จีนดั้งเดิม, ชวา, ชิเชวา, ซามัว, ซีบัวโน, ซุนดา, ซูลู, ญี่ปุ่น, ดัตช์, ตรวจหาภาษา, ตุรกี, ทมิฬ, ทาจิก, ทาทาร์, นอร์เวย์, บอสเนีย, บัลแกเรีย, บาสก์, ปัญจาป, ฝรั่งเศส, พาชตู, ฟริเชียน, ฟินแลนด์, ฟิลิปปินส์, ภาษาอินโดนีเซี, มองโกเลีย, มัลทีส, มาซีโดเนีย, มาราฐี, มาลากาซี, มาลายาลัม, มาเลย์, ม้ง, ยิดดิช, ยูเครน, รัสเซีย, ละติน, ลักเซมเบิร์ก, ลัตเวีย, ลาว, ลิทัวเนีย, สวาฮิลี, สวีเดน, สิงหล, สินธี, สเปน, สโลวัก, สโลวีเนีย, อังกฤษ, อัมฮาริก, อาร์เซอร์ไบจัน, อาร์เมเนีย, อาหรับ, อิกโบ, อิตาลี, อุยกูร์, อุสเบกิสถาน, อูรดู, ฮังการี, ฮัวซา, ฮาวาย, ฮินดี, ฮีบรู, เกลิกสกอต, เกาหลี, เขมร, เคิร์ด, เช็ก, เซอร์เบียน, เซโซโท, เดนมาร์ก, เตลูกู, เติร์กเมน, เนปาล, เบงกอล, เบลารุส, เปอร์เซีย, เมารี, เมียนมา (พม่า), เยอรมัน, เวลส์, เวียดนาม, เอสเปอแรนโต, เอสโทเนีย, เฮติครีโอล, แอฟริกา, แอลเบเนีย, โคซา, โครเอเชีย, โชนา, โซมาลี, โปรตุเกส, โปแลนด์, โยรูบา, โรมาเนีย, โอเดีย (โอริยา), ไทย, ไอซ์แลนด์, ไอร์แลนด์, การแปลภาษา.

Copyright ©2024 I Love Translation. All reserved.

E-mail: