5.6 CONTENT OF SVVP/SR, SVVP/AD & SVVP/DD SECTIONS
These sections define the review, proof and tracing activities in the
SR, AD and DD phases of the lifecycle. While the SPMP may summarise
these activities, the SVVP should provide the detailed information. For
example the SPMP may schedule an AD/R, but this section of the SVVP
defines the activities for the whole AD phase review process.
These sections of the SVVP should avoid repeating material from
the standards and guidelines and instead define how the procedures will be
applied.
ESA PSS-05-0 recommends the following table of contents for the
SVVP/SR, SVVP/AD and SVVP/DD sections