9% of Costs as adjusted in accordance with the provisions of the Contract
The Employer reserves the right to directly procure any and make arrangements for the Contractor to take delivery (on time in accordance with the programme) on site for the contractor’s installation works. A 5% Contractor's F shall be imposed on the cost of such direct equipment/materials procured by the Employer up to a maximum of 25% of the value of equipment/materials described in the BoQ.
Any other equipment/materials proposed to be directly procured by the Employer over and above the maximum 25% value shall be subject to 9% Contractor's Fee.