1. For Nov 7-8, 2016 CBA Will replace termination at RMU 7 I discuss with you. And the first you will postpone to Jan 2017 and now I accept to move back to done the job on Nov 7-8, 2016 and our staff plan to handle this job Khun Radomphol phone 094 185 9035 (Main Contact in Change person) or Khun Songpon 095 207 0649 (Option) and man power 8 person
2. For Nov 5-6, 2016 CBA Will replace termination at RMU 6 for 3x120 Sqmm, 6 End with time 2 Day and testing (If CBA done job quickly the quality of working must be lower that the normaul time and this job CBA normally I worry nthe time every short give to us and time not matching with us. Because CBA must be do the job on RUM 7 at Nov 7-8, 2016 (for replace Termination 1x240 Sqmm, 9 End) and Why I not sign back P.O. to Dow. Because at that time CBA have job many customer they already booking and This job RMU 6 I also mobilized same team and the same person in charge to do and CBA must be continue job from earlier morning until midnight every day. Because I not choice and I apologized that for this time made all of you not too happy with us. And I will try my best to support all of you both. And I will Keep Spare for our staff Khun Wittawat to have safety orientation as well and this job I worry job timing not matching with us and