Minutes dated 26/11
1. There was a leak of distillation tower. planning &production team are solving and will update.
2. RM of NMP will arrive next month. We can use it to produce for Ultra order by 4/1/16
3. With regard the boxes are not full order like EOS,BELMAN,KOFA. Cs noted and give us 3 month to discuss with the rest to solve it out.
4. Scientific customer need only new batch while order volume does not reach our minimum. The result is that we cannot sell the remaining from production to anyone. Cs noted and try to push customer to order full batch. If not, may need to buy locally. Will keep updated.
5. The goods that have order volume more than MOQ, domestic team will adjust the figures to minimize out of stock problem
6. Goods located at WFT can be delivered within 1 day. Cut off time is 3 p.m.
7. NCI will do annual shutdown for thermo oil and steam boiler during 22-04/1 total 15 days. Orders that affected, planning team will send email out.
Remark: Thermo have adjusted to fit a carton already.