Each item of Plant and Materials shall, to the extent consistent with the Laws of the
Country, become the property of the Employer at whichever is the earlier of the
following times, free from liens and other encumbrances:
(a) when it is delivered to the Site;
(b) when the Contractor is entitled to payment of the value of the Plant and
Materials under Sub-Clause 8.10 [Payment for Plant and Materials in Event of
Suspension].