According to Triangle Engineering had been confirm Lay out for Machine for responsible by milestone on 13 October 2016 ,So TPCI would like to know progress for Machine Load data and please define target date to send Machine load data to Triangle Engineer for RDF Foundaton because this data has obstruct for RDF PLANT construction to be delay for Master schedule
please expedite and define taget date send back to Triangle Engineer and TPCI