1. When did you know KBT TH need add more new machine?
2. Why you submit P.C.R sheet to DMVN not meet regulation in SQAM
3. last time you know same problem with Nozzle 0240 => Why you don't improve with this PCR ?
4. Send to me Compare result between old & new machine
5. Submit 5M1E sheet. ( DMVN's Format ).
6. Submit Cpk of Nozzle make by new machine.
7. Compare result for Cpk of old and new machine.
8. Make clear about capability of current machine and new machine for Nozzle 0200 & 0250.
9. The current machine are manufactor for 2Nozzle 0200 + 0250 Right?
10. After applied the PCR new machine will manufactor for 2Nozzle 0200 + 0250 too right?
11. As Mr. DIEP explain in his Email:
- Can you use 1 machine to produce 1 part no and 1 remaining machine to produce 2 part no => We only need to solve 1 PCR.
=> Please thinking about reject PCR for Nozle 0200 or 0250. if you don't reject any PCR => please clearly explain to me Why?
Please answer enough my question above no later than 9AM tomorrow morning, Because we have internal meeting about this matter
If you don't answer on time, we will automatic understand you are not cooperation to DMVN.