About PR Nong Process. K .Suphon and GM singed 1-2 Days sign in PR . And Wait K. Sothea release …… Days . But PR copy sent to K.Seng about 7 Days.
27 Dec 14 – 5 Jan 15 is Holiday of Thailand. ( Can not make quotation )
Never mind. Khun Nong and Khun Seng start to coordinate About Qutation of Shop When PR Copy sent Khun Seng Already . ( Date K.Seng recived to sing in PR ) Because GM not sign in Qutation Same If PR not complete Signature .
About Product come in . Koh Kong Sent E-Mail to Khun Toom and K.Somnang every Time . And today Have Product of Aiyara Company come in . Koh Kong sent to Mail About PO to K Toom Already . Khun Nong and K.Seng tell you again or not .
OK . Starting today . All Product of Khun Nong Come in . K. Seng tell you beford Product come in 1 Day and send only copy PO to you. For received product next day . As Invioce send to you the same day Product come in .
Please, Khun Suphon Acknowledged or Recommended.