Hi Marvyn,
Please find attached some additional information related to the installation of the sliders + a link here below where you can watch some interesting videos (the last ones) showing installation of rides from WWW in some of their previous projects.
Important note:
Attention at the coordination with the M&E as most of the piping works located under & just around the rides should be completed when we will start the installation of the steel towers + fiberglass (or they piping works need to be done after, but it will be too late I think).
Otherwise the machines (cranes, elevators,…) won’t be able to circulate effectively.