If an extension of time is granted in accordance with this clause 4, provided that those costs are not also reimbursable pursuant to clause 19 or clause 21, the Company will reimburse the Contractor for any costs reasonably incurred directly thereby and for on-Site overheads attributable to the delay, but without regard to off-Site overheads, or profit or for any other cost, loss, expense or damage.