MILESTONE 4 Phases 10 – 11 - 12
shown for production startup level progress
PHASE 10.0 FINAL PRODUCTION DEVELOPMENT START-UP
10.1 Assemble/update final drawings/manufacturer bid package
10.2 Select desired contract manufacturer(s)
10.3 Update design as necessary to meet manufacturer tooling and production requirements (requested tooling/design changes as necessary)
10.4 Release Tooling program
10.5 Order OEM components/PC Boards
10.6 Confirm Assembly design – all components delivery/scheduling
10.0 DELIVERABLES: Final Production Design /ProE model. with tooling change requests. Consulting & Troubleshooting.
PHASE 11.0 PRODUCTION START-UP
11.1 Release/Award final drawings manufacturer package
11.2 Final production tooling procurement
11.3 Tooling / testing runs – pilot parts
11.4 Assemble production assembly line
11.5 Initial production part product performance review
11.0 DELIVERABLES: Production First Line articles. Consulting & Troubleshooting. Quality Review.
PHASE 12. PRODUCTION LAUNCH