The updating of adjustment as per Syngenta comments show as follows.
1. 2.2 Fall protection at unloading platform: Committed date Saturday 10 January 15 : Status – Done.
2. 2.3 Loading hopper to sorting table should install plate to arrange corn in 1 layer and reduce impaction: Committed date Monday 12 January 15 : Status – Done.
3. 3.4 Hopper shooting from incline conveyor to fill conveyor should have plate for reducing impaction and have opening : Committed date Sunday 11 January 15 : Status – Done.
4. 4.2 Protect rain to come inside Bin no.1, no.2,no.13, no.14: Required date 31 January 15 : Status – Plan to finish by metal sheet.
5. 4.3 Top bin grating door support: Committed date Sunday 11 January 15 : Status – The tools prepare will install when the bins empty.
6. 4.4 Fire escape ladder from dryer second floor: Committed date Sunday 11 January 15 : Status – Done.
7. 5.4 Platform for maintenance pulley at sheller top floor: Committed date 14 January 15 : Status – 98% Will complete as committed for sure.
For your information.
Any comment please let me know.