We plan to stack A3EG level 2 on Mon 3 Mar 14
For lower level 95% completed, remaining some loose item to erection please continue to finish on this week as we have material on hand.
Handrail start weld from now.
Grating install on this week.
All column and bracing please start to erection from today.
We will do PFP in situ.
On loose item of level 2 outstanding Khun Sutin will give the delivery date to me by today.
Night shift require on this area to finish on time.
Scaffolding require on every column for survey and weld after level 2 stack.