Test Plan
• Everyone is to move to the 3.6.33 that was built tonight
• We need to plan for regression testing of all features executed over the last few sprints this week (5B and 5C) with a target completion of Monday/Tuesday at the latest giving us a week to complete (allow to identify any regression tests while development continues to fix defects)
• SDL will be executing the regression that we have provided them (not including the 5B and 5C content)
• Please add regression tests planned this week into the folder Blackcomb RTM in MKS. We will be tracking all our testing and progress using that folder for this upcoming week (don’t forget to keep to the correct folder levels)
• For RTM we are to support fresh installs and upgrades only from EPR5. We are not supporting upgrades from EPR4 to RTM. All pre-release customers must go to EPR5 (3.6.13) before they go to RTM (note we will support EPR5 with BBOS support to RTM)
• For the final week Nov 5 to Nov 12, we will be doing one final regression pass and P1 tests. The goal of this week is to get one week of soak in Alpha/RIM IT before we release
• SRR is planned for Nov 12