I must identify an error from the Recovery Remaining work schedule issued. Foundation T01 is identified as complete, which is incorrect. It will be deemed complete when Powerchina has signed off on corrective action for the grout repairs, installation of final backfill (around the pedestal), completion of the hardstand, completion and Powerchina acceptance of the Handover process. I would suggest that you carry a line item for Handover process. This will also be true for road sections as well.