Looking ahead at the occupancy levels after Songkran, please arrange for room blocking to be grouped together on 1 side of the resort so that Engineering can do maintenance works on the other side.
I suggest you start May by blocking all guests in buildings 1-4 as much as possible.
Then once Engineering has made progress on the maintenance of the rooms in buildings 5-8 + Boat Suites, then coordinate with them to swap room blocking so rooms are blocked in buildings 5-8 so work can be done on buildings 1-4.
By cc to Eak & Khoy, work out a detailed rooms maintenance plan for buildings 5-8 during May + a plan for buildings 1-4 during June.
Focus on woodworks of railings, bathrooms, tiling, a/c maintenance, etc.
I’m looking for deep cleaning & maintenance to get the rooms ready for the shoulder season.
Present to me on this Friday 18 April in my office at 11:00 hrs.
If you need additional manpower, say how much, when & where, so we can make the arrangements.
Looking ahead at the occupancy levels after Songkran, please arrange for room blocking to be grouped together on 1 side of the resort so that Engineering can do maintenance works on the other side.
I suggest you start May by blocking all guests in buildings 1-4 as much as possible.
Then once Engineering has made progress on the maintenance of the rooms in buildings 5-8 + Boat Suites, then coordinate with them to swap room blocking so rooms are blocked in buildings 5-8 so work can be done on buildings 1-4.
By cc to Eak & Khoy, work out a detailed rooms maintenance plan for buildings 5-8 during May + a plan for buildings 1-4 during June.
Focus on woodworks of railings, bathrooms, tiling, a/c maintenance, etc.
I’m looking for deep cleaning & maintenance to get the rooms ready for the shoulder season.
Present to me on this Friday 18 April in my office at 11:00 hrs.
If you need additional manpower, say how much, when & where, so we can make the arrangements.
การแปล กรุณารอสักครู่..