For a cost ratio that is greater than 10, the optimal solution is obtained at another extreme point, representing an effective shift duration of 10.3 hours and total overtime of 18.6 hours, allocated to both Tool 7 and Tool 4. When the cost ratio is equal to 10, any convex combination of the above two optimal solutions is also optimal.