Regarding to EIA’s project schedules, we would like to estimate time line of construction’s schedule as following items :
1. Himalai’s Earth Works & Infrastructure
Start : 15 Dec 2016 – End of May’ 2017
2. Himalai’s Building Construction
Start : Mid Feb’s 2017 – Beginning of Sep’ 2018
3. Grand Himalai’s Show Building D9
Start : Mid Dec’ 2016 – Mid April’ 2017
4. Grand Himalai’s Building Construction
Start : Mid Feb’s 2017 – Beginning of Sep’ 2018
Soft opening : Sep’ 2018
Grand opening : Dec’ 2018
If you have any commend. Do not hesitate to contact us for any change of time line.