Single Minute Exchange of Die (SMED)
SMED was developed by Shigeo Shingo in Japan in the sixties and early seventies at Toyota and other Japanese firms. The impetus was to reduce costly inventories and improve efficiency.
An important foundation to the SMED system is the distinction between changeover work that occurs while the machine is not running, called Internal Setup, and preparatory work that occurs while the machine is running, called External Setup. At the point in time when SMED was developed, almost all changeover work was performed while the machine (press) was down.
The SMED philosophy breaks down into four stages:
1.In the preliminary stage, all setup work is combined. There is no distinction between internal and external work.
2.In the second stage, external setup and internal setup are identified and separated.
3.In the third stage, work that was previously included in the internal setup is transferred to external setup.
4.The fourth stage requires relentless and continuous improvement of all work elements within the internal and external setup (Kaizen).
A useful comparison is the pit crew of a racing team changing tires.
If the tools and parts are not prepared until the car enters the pit, then the pit stop will be lengthy. If the parts and tools are prepared beforehand (External Setup), the crew's every move is choreographed for efficiency, and special tools and fittings are used to increase speed, then the pit stop will be short.
Changeover Time Reduction Techniques
Specific techniques to reduce changeover time are:
Staged Tooling and Fixtures
If a part or tool must be placed into a fixture prior to an operation, such as machining, add a fixture so that while one part or tool is in the machine, the second can be set up in the fixture.
Operations Conducted in Parallel
Consider the pit crew example again: if the four tires are changed simultaneously by four crew members that pit stop is a lot faster than if the crew moves from tire to tire in sequence.
Standardization
Tools that are the same size with the same attachment location can be changed much more quickly. Consider how long it would take a pot crew to change tires if the replacement tire had a different lug nut configuration. In the same vein, a common die height allows the shut height of the press to be set to a common dimension.
Standardized attachment points and methods reduce confusion and the number of fasteners - saving time. Standardization also applies to tool storage organization so that tools can be quickly located. See the 5S tutorial of the Toolbox for additional discussion of workstation organization.
Quick Attachments
Clamps, cams, and u-shaped washers are used for quick attachments. If a bolt can be pre-tightened during external setup, then it only needs one final turn to provide clamping force during internal setup. Another example to consider is the quick-release hub on a bicycle tire, which facilitates rapid changeover by a lever and cam device so that a wrench and the time that goes with it is not required.
No-Adjust Tooling
Use locating pins, guides, and fixtures to completely eliminate adjustment.
Duplicate Tooling
Duplicate tooling can minimize or eliminate the need for changeovers, and the cost can quickly be offset by reduction in inventory and set-up labor costs. Simple pre-set gauges and templates can speed up changeovers without large expense.
Assisted Tool Movement
Large dies or other heavy tools can be moved much faster using dedicated die carts, roller tables, or small conveyors than with forklifts or cranes. Mechanized tool change equipment allows pre-staging of the replacement tool, and may also facilitate changeovers by the base equipment operator without additional indirect labor.
Benefits of reduced changeover time
By incorporating the above methods, massive dies are commonly changed in less than 10 minutes - setups that used to take hours. Benefits of reduced changeover time extend beyond the direct reduction of inventory to include:
•Reduced lead times and improved responsiveness to customers.
•Flexibility to respond to changes in demand.
•Improved product quality from quicker information feedback.
•Improved visual control and plant communication.
•Reduction of indirect costs for material movement, counting, and transaction processing.
Single Minute Exchange of Die (SMED)SMED was developed by Shigeo Shingo in Japan in the sixties and early seventies at Toyota and other Japanese firms. The impetus was to reduce costly inventories and improve efficiency.An important foundation to the SMED system is the distinction between changeover work that occurs while the machine is not running, called Internal Setup, and preparatory work that occurs while the machine is running, called External Setup. At the point in time when SMED was developed, almost all changeover work was performed while the machine (press) was down.The SMED philosophy breaks down into four stages:1.In the preliminary stage, all setup work is combined. There is no distinction between internal and external work.2.In the second stage, external setup and internal setup are identified and separated.3.In the third stage, work that was previously included in the internal setup is transferred to external setup.4.The fourth stage requires relentless and continuous improvement of all work elements within the internal and external setup (Kaizen). A useful comparison is the pit crew of a racing team changing tires.If the tools and parts are not prepared until the car enters the pit, then the pit stop will be lengthy. If the parts and tools are prepared beforehand (External Setup), the crew's every move is choreographed for efficiency, and special tools and fittings are used to increase speed, then the pit stop will be short.เทคนิคการลดเวลาปรับเปลี่ยนเทคนิคเฉพาะเพื่อลดเวลาเปลี่ยนเป็น: เครื่องตกแต่งและเครื่องมือตามขั้นตอนถ้าต้องวางชิ้นส่วนหรือเครื่องมือในการติดตั้งก่อนการดำเนินการ เช่นเครื่องจักร เพิ่มการติดตั้งเพื่อที่ขณะหนึ่งส่วนหรือเครื่องมือเครื่องจักร ที่สองสามารถตั้งค่าในการติดตั้ง การดำเนินงานที่ดำเนินการแบบขนานพิจารณาตัวอย่างลูกเรือหลุมอีก: ถ้าเปลี่ยนยางสี่ โดยสี่ลูกเรือพร้อมกัน ที่หยุดจะเร็วมากกว่าถ้าลูกเรือย้ายยางยางในลำดับนั้น มาตรฐานเครื่องมือที่มีขนาดเดียวกันกับสิ่งที่แนบมาตำแหน่งเดียวกัน สามารถเปลี่ยนแปลงได้อย่างรวดเร็ว พิจารณาระยะจะใช้ลูกเรือหม้อเปลี่ยนยางเปลี่ยนยางมีการกำหนดค่าต่าง ๆ ถั่ว lug ในหลอดเลือดดำเดียวกัน ตายสูงทั่วไปให้ความสูงปิดของกดเพื่อตั้งค่ามิติทั่วไปคะแนนมาตรฐานที่แนบและวิธีลดความสับสนและหมายเลขของรัด - ประหยัดเวลา มาตรฐานยังใช้เครื่องมือเก็บข้อมูลองค์กรเพื่อให้เครื่องมือสามารถอยู่ได้อย่างรวดเร็ว ดูสอน 5S ของกล่องเครื่องมือสำหรับการอภิปรายเพิ่มเติมของเวิร์กสเตชันองค์กร สิ่งที่แนบมาอย่างรวดเร็วแคลมป์ กล้อง และคุณทรงผ้าใช้สำหรับสิ่งที่แนบมาอย่างรวดเร็ว ถ้าสลักสามารถ tightened ก่อนระหว่างการติดตั้งภายนอก แล้วมันเพียงต้องการหนึ่งสุดท้ายเปิดให้หนีบแรงระหว่างการติดตั้งภายใน อีกตัวอย่างหนึ่งที่ควรพิจารณาคือ ปลดฮับบนยางจักรยาน ที่เปลี่ยนอย่างรวดเร็ว โดยอุปกรณ์ก้านและ cam เพื่อให้ประแจและเวลาที่ตรงกันไม่จำเป็น ไม่มีปรับการขับรถใช้ค้นหาพิน ไกด์ เครื่องตกแต่ง และการปรับปรุง เครื่องมือซ้ำเครื่องมือซ้ำสามารถลด หรือกำจัดต้อง changeovers และต้นทุนได้อย่างรวดเร็วจะตรงข้าม โดยการลดต้นทุนแรงงานสินค้าคงคลังและตั้งค่า เครื่องวัดตั้งไว้ง่ายและแม่แบบสามารถเร่ง changeovers โดยไม่มีค่าใช้จ่ายขนาดใหญ่ เครื่องมือที่ช่วยการเคลื่อนไหวแม่พิมพ์ขนาดใหญ่หรือเครื่องมืออื่นหนักสามารถย้ายได้เร็วด้วยตายเฉพาะรถ ตารางลูกกลิ้ง สายพานลำเลียงขนาดเล็กกว่า หรือรถยกหรือเครน เปลี่ยนมือ mechanized ให้จัดเตรียมล่วงหน้าของเครื่องมือเปลี่ยน และยังอาจช่วยให้ changeovers โดยการดำเนินการฐานอุปกรณ์โดยไม่ต้องเพิ่มแรงงานทางอ้อม ประโยชน์ของเวลาเปลี่ยนลดลงโดยผสมผสานวิธีการดังกล่าวข้างต้น แม่พิมพ์ขนาดใหญ่มีการเปลี่ยนแปลงทั่วไปใน 10 นาที - ตั้งค่าที่ใช้จะใช้เวลา ประโยชน์ของเวลาเปลี่ยนลดขยายเกินลดโดยตรงของสินค้าคงคลังจะรวม:•ลดการระยะเวลาและปรับปรุงการตอบสนองลูกค้า •Flexibility to respond to changes in demand. •Improved product quality from quicker information feedback. •Improved visual control and plant communication. •Reduction of indirect costs for material movement, counting, and transaction processing.