Dear all
Summary of our meeting on 26 Apr 2016 for substation start erection activity on 9 May.
To execution this work need room conditions and handover date as below
Control room plan for handover area not late than 9 May 2016
- Floor epoxy for first layer
- Door Installation
- Open block out for ventilation work (Fan & Fresh air)
- Paint Wall and ceiling
- Finishing Floor block out
Battery room plan for handover area not late than 9 May 2016
- Floor epoxy
- Wall epoxy 1.5 meter
- Paint over 1.5 meter
- Ceiling gypsum
- Door Installation
- Open block out for ventilation work (Fan & Fresh air)
- Finishing Floor block out
Cable room plan for handover area not late than 9 May
- Floor finishing
- Door Installation
- Open block out for ventilation work (Fan & Fresh air)
- Paint Wall and celling
- Finishing Floor block out
MV room plan for handover area not late than 15 May
- Galvanize Base frame for MV switch gear
- Floor epoxy for first layer
- Door Installation
- Open block out for ventilation work (Fan & Fresh air)
- Paint Wall and ceiling
- Finishing Floor block out
Power Transformer room plan for hand over not late than 20 May
- Wall and plastering
- Paint Wall and ceiling
- Casting ceiling for fire escape in front of PTR room
Power Transformer room plan for hand over not late than 30 May
- Crunch rock & grating for oil pit
- Galvanize Trench cover
- Galvanize Checker plate
- Open block out for ventilation work
- Louver and door
Main power cable
- Block out at front side of pump room 500*1500
- Block out at back side of pump room 500*1500
- Coring for HDPE - 115 kV & 22 (Size will confirm from PEA, Position and D-wall reinforce will design by Structure designer)