Dear Jamie,
Have a quick review and adding my comment as follows;
· Contract BOQ-Qtn is to complete to all measured items, Item 7 to state “excluded”.
· Total Summary is to separate for the steel measured in tonnes, m2 and linear m.
· Item 3 & 4 measured from Tertiary Steel drawings, new items with material grade “Type V, VI and VII” are to specify.
· Padeyes quantities are found excessive. This item may consider moving in Item 1 - Primary steel.
· All drawings using for measurement are to list in footnote with the revision specifie