Today, I have met Japanese peron in charge of Thai Obayashi, and he informed me that Planned construction site
of BCS 2 is in Residential Area of Samutprakarn province’s land plan in 2013 and It might not use for any factory
construction. So, We are afraid that we can’t start construction work from January,2014.
Also, he told us that it takes more than 6months to take building permission after applied if the construction cost more than
Baht 200 million. As you may know, our construction cost approximately Baht 300 million, so it takes 6months to obtain
permission even we can construct new warehouse.
Please contact following Obayashi PIC and start information gathering from Samutprakarn Ministry of Industry, Prefectural
government and any other relative public agency.
In the worst case, we will have to suspend BCS 2 plan completely.
Person in charge of Thai Obayashi
Navin Lapwanitch (MR)
e-mail: navin.la@thaiobayashi.co.th
tel:085-155-6107