Install bell nipple. set wear bushing.
M/U 8 3/4" BHA.
Shallow test MWD, then RIH to tag top of cement at 841.4 m.
Take SCR. Perform kick drill.
Drill out 9 5/8" casing shoe, then drill into new formation 5 m. circulate.
Perform LOT by Dowell unite.
Drill ahead to 1171 m.