Regarding 4th shipment for Thep Viet Co. with 10x40’HC, they send order on 27th May to required ETA on 6/6. But we can’t do it due to production damage in last week, now ETA will be on 12/6. Because this delay will be affected to 5 sub-contractors at job site, so they need our explanation letter to submit the owner and consultant.
I modify letter of Nam Minh Hoang for this requirement. Please comment and sign it to send me back today. They have the meeting with owner tomorrow morning.
Once again we apologize for the inconvenience may cause from this delayed.
We put our best effort to ensure that your next shipment will meet the schedule.
Thank you for your understanding and supported.