Thank you.....this report details work before the site visit in 2011. From our conference call, I was under the assumption that this information was from a report after our 2011 site visit. The time it has taken to address the MSSF findings and corrective actions is not acceptable. Given that we have a target completion date of June 2013, I do not see how we can possibly close this finding. For the consultant to do a correct analysis, they will possibly have to do significant field work including drilling to get good field data for the model.
At this time, given the delay in taking action for these findings, I need to see a detailed schedule for what our next actions are. I would like to know:
When will consultant be onsite?
What is the consultants scope of work?
What do we expect the consultant to do?
When will consultant provide us with a proposed scope of work and cost estimate
What will be the cost ?
When will they finish the field work and provide us with a Factor of Safety and what we do to manage the existing impounds
I would like to have a conversation with the consultant so that I fully understand what the issues are. I am available next week for a conference call with the consultant. Please let me know when they would be available.
Regards,