Dear Vincent,
I input JML data for you already. And I apologize for wrong data of slide 27 and now I update slide 27 finish.
But slide 26 have many reason : Budget excavation plan 2013 : We planning this data about september 2012 for prepared budget data for raw material and overburden .
We estimated the ending stock of december 2012 (32000 BCM.) was less than actual stock (113256.35 BCM.) to much.Different about 80,000 BCM.
And after that on January 2013 I prepared graph for you I looked forecase and used actual stock end of december 2012.
Now I compare data end of march 2013 for you : actually , On March 2013 we excavator was less than budget plan different about 33,000 BCM.
Thus , When I summary every data in this graph is deifferent when you compare with previous presentation (January 2013).