Dear K.1
CC : K.Theera
Refer : Memo No.PJM-DDC-145/2015
Please kindly be informed working schedule @ actual site as below.
1. Working Schedule
As the customer requested us must be finish install kitchen equipments within 7 days (From 01 July 2015 until 07 July 015) so please kindly assign your install team action by follow as installation plan.
2. Working Documents
- When you will action at actual site please do the working documents in advance 1 days (As attached file)
- For hot working please do the working documents in advance 2 days (As attached file)
Remark : Please checked at actual site and arrange the kitchen equipments into the area and if you have some question please do not hesitate direct contact k.suphan as 081-875-9786 kha.