Sorry, my response is delay.
I have questions about your report.
・This report is intermit report, isn’t it?
・I couldn’t understand why did dimension NG produce?
・I couldn’t understand root cause situation.
Please make clear the situation at occurrence with some description and photo.
-------------------------
Hello:
This one setup part was missed place back in the line after 1st part inspection. The part handling and part containment are not good. And, the poor 5-S within the line on new operator(s) has to be addressed this issue in the 8D.
SWS-Thailand did re-check all the inventory, previous data, Cpk, we found no bad part.
So sorry again for this trouble.