Item One Kone are doing survey and shafts and will advise any comments on Friday
· Kone and Times to agree delivery and storage arrangements for the elevator materials due early April
· Decision on wall colour. NS came to site this morning, were very helpful. Hassel will issue details of sample board to be made on next Monday for NS to make and to be hung on the façade for review
· Decision on aluminum color. The three sample as issued have been rejected as the selection is not normal and not adequate. Times to get the full range of standard colors for owner/designer selection